Tuesday, September 26, 2006

Cabin Addition Update

Carl and George were up to the cabin over the weekend. They wired the new addition.

Work that can be done now:

Insulate the walls, the wiring is finished. Not the ceiling, the duct work still needs to be run.

Connect and run duct work from the furness to the new room and honeymoon suite. See Carl for details.

Finish front of addition. Cover with plywood.

Build overhang on side of addition.

Shingle the roof.

Put in exterior doors.

Apply siding.